Overpaying contractors is one of the most common ways construction budgets go wrong. It rarely happens through one big mistake. It happens through small extras on every running bill. Checking each bill before you pay protects your budget.

What a Running Bill Should Show

If your contractor’s bill does not show this, ask for it before paying.

Step-by-Step Bill Checking

  1. Measure on site. Measure the work actually done, such as brickwork in square feet, concrete in cubic feet and steel in kilograms.
  2. Compare with drawings. Quantities should not exceed what the drawings require.
  3. Check rates against the BOQ. Rates must match the agreed rates. New items need written approval first.
  4. Check quality before quantity. Do not pay for work that has to be redone.
  5. Track materials you supplied. If you bought cement or steel yourself, the contractor should not charge for it.
  6. Keep retention. Hold back a small percentage until the work is complete and defects are fixed.

Common Billing Problems

Why a BOQ Makes Billing Easier

When the contract is based on a BOQ, every bill is checked against the same list of items and rates. Without one, every bill becomes an argument.

Get Your Bills Checked

Design Estimations Engineering Services prepares and verifies contractor and sub-contractor bills and interim payment certificates for houses and commercial projects in Lahore. Call or WhatsApp +92 328 9900555 for a free consultation.

Leave a Reply

Your email address will not be published. Required fields are marked *

Secret Link
Call Now Button