Overpaying contractors is one of the most common ways construction budgets go wrong. It rarely happens through one big mistake. It happens through small extras on every running bill. Checking each bill before you pay protects your budget.
What a Running Bill Should Show
- Each item of work, using the same item names as your BOQ
- Quantity done in this period and total quantity to date
- Agreed rate for each item
- Amount for this bill and total paid so far
- Deductions such as advances and retention
If your contractor’s bill does not show this, ask for it before paying.
Step-by-Step Bill Checking
- Measure on site. Measure the work actually done, such as brickwork in square feet, concrete in cubic feet and steel in kilograms.
- Compare with drawings. Quantities should not exceed what the drawings require.
- Check rates against the BOQ. Rates must match the agreed rates. New items need written approval first.
- Check quality before quantity. Do not pay for work that has to be redone.
- Track materials you supplied. If you bought cement or steel yourself, the contractor should not charge for it.
- Keep retention. Hold back a small percentage until the work is complete and defects are fixed.
Common Billing Problems
- Charging for full slab area including openings and shafts
- Measuring plaster on both sides when only one side is done
- Extra steel quantities not supported by the BBS
- Rates changed without agreement
- Items billed twice in different bills
Why a BOQ Makes Billing Easier
When the contract is based on a BOQ, every bill is checked against the same list of items and rates. Without one, every bill becomes an argument.